April 4, 2006 Auction at Lexington Country Club
June 22, 2006 Ground Breaking Ceremony On-Site
June 13, 2006 Physical Ground Breaking Begins
October 31, 2006 Pre-Construction Pricing Ended
October, 2006 Selection Process Begins
November, 2006 Foundations on many Buildings Began
November, 2006 Reached Our 100th Sale
December, 2006 Curbs Being Installed
December, 2006 Walls on mnay Buildings Began
December, 2006 Community Boat Ramp Installed
January, 2007 Lighting Selections Began
January, 2007 Over 15 Buildings with Concrete Walls
February, 2007 Boat Docks Being Installed
March 25, 2007 Framing of Buildings Began
March, 2007 Paving the Roads Began
April, 2007 Roofing of First Buildings
April, 2007 Only 18 Units Remain
May, 2007 Dry Wall began on Building 27, 28, 29
May, 2007 All Electrical Power Installed
June, 2007 Fence Along 378 Erected
June, 2007 Over 80% of Foundations Finished
June, 2007 Steel Structure for Clubhouse Installed
July, 2007 Gave away 1,000 Beach Balls at Gilbert Peach Festival
July, 2007 95% of Foundations Installed
August, 2007 Community Pool Installed
August, 2007 Preparation for Tennis Court Began
September 28, 2007 1st Unit Closes at Hammock Bay
September 25, 2007 Gave away 1,000 Beach Balls at Lexington Fun Fest
September, 2007 Construction of Walking Paths Begin
September, 2007 Landscaping Begins on Entrance
October, 2007 Drywall the Club House
October, 2007 Finalization of Waterfall near Ponds
Novemner 20, 2007 Closing on Hammock Bay
November 27, 2007 Pool Deck Installed